Penataan Lima RW di Kedaung Kali Angke Sudah 65 Persen

Five RWs Arrangement in Kedaung Kali Angke Already 65 Percent

The West Jakarta Public Housing and Settlement Sub-agency reports five RWs arrangement in Kedaung Kali Angke, Cengkareng, West Jakarta has reached 65 percent.

We' re currently focusing on installation of u-ditch channel and road casting

West Jakarta Public Housing and Settlement Sub-agency Head Suharyanti said those RWs are 01, 02, 03, 06 and 08. Its arrangement includes repairing neighborhood road and drainage, installing absorption well, guide tiles for disabled, vertical garden, plant pots, sorting bins, benches, mural painting, street name signposts, convex mirrors, reflection lanes and streetlight.

"We' re currently focusing on installation of u-ditch channel and road casting," he expressed, Wednesday (11/13).

Arrangement Under Joglo Toll Road Has Reached 90 Percent

This work has been carried out since October and is targeted to be finished in December.

"To do it, we have spent Rp 14 billion," he stated.

Linked News
Popular News indeks
  1. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye790 personTiyo Surya Sakti
  2. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye697 personDessy Suciati
  3. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye636 personTiyo Surya Sakti
  4. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye542 personNurito
  5. Gov Pramono: Jakarta Prepared to Adopt Weekly WFH Scheme

    access_time30-03-2026 remove_red_eye444 personDessy Suciati